News Release
OPENING:
The regular meeting of the Board of
PRESENT: ABSENT:
Otto L. Nicely, Commissioner
Third Commissioner Seat Vacant
Alison Grimes, Clerk – on vacation
D. Joan Brown, Deputy Clerk
The minutes for the
Motion – Tom Second – Otto
Ø
JOURNAL #130, RESOLUTION #02-08-437
The following Resolutions were submitted for consideration and approved:
Payment of Vouchers
Motion – Otto Second - Tom
Ø
JOURNAL #130, RESOLUTION # 02-08-438
Transfer of Funds #54 –
Motion – Tom Second - Otto
Ø
JOURNAL #130, RESOLUTION # 02-08-439
Transfer of Funds #55 –
Motion – Otto Second - Tom
Ø
JOURNAL #130, RESOLUTION # 02-08-440
Amended Official Certificate #8 - $1,254,460.60
Motion – Tom Second - Otto
Ø
JOURNAL #130, RESOLUTION # 02-08-441
Dedication of
Motion – Otto Second - Tom
Ø
JOURNAL #130, RESOLUTION # 02-08-442
The Commissioners discussed installation of directional signs in the parking area, landscaping, and painting at the fairgrounds.
Bids were received from the following:
AKIL $185,956.00
Eagle Bridge $206,707.58
Harper Structures $205,065.25
R. G. Zachrich $187,179.00
Vernon Nagel, Inc. $202,121.45
Napoleon, OH
The Engineer’s Estimate is $191,465.00
Bids were received from the following:
AKIL $181,974.90
B. Hill’z Excavating $190,335.40
Eagle Bridge $203,938.13
Harper Structures $199,419.00
R. G. Zachrich $182,655.44
Vernon Nagel, Inc. $193,135.85
Napoleon, OH
The Engineer’s Estimate is $191,477.50
Bids were received from the following:
AKIL $167,634.15
B. Hill’z Excavating $181,395.25
Eagle Bridge $185,008.22
Harper Structures $193,775.00
R. G. Zachrich $169,750.00
Vernon Nagel, Inc. $182,356.85
Napoleon, OH
The Engineer’s Estimate is $168,352.50
Accept
Motion – Tom Second - Otto
Ø
JOURNAL #130, RESOLUTION # 02-08-443
Mr. Davis also
presented his weekly update. He reported
that ODOT has requested that 20% of projects be bid in the first quarter, 30%
in the second quarter, 30% in the third quarter, and 20% in the
fourth quarter each year in order to receive better bids.
The next bridge
project to be started will be replacement of a small concrete structure on
The Engineering
Department will assist in driving the posts at the fairgrounds for placement of
the directional signs.
The parking lot
project at the KeyBank location should be completed in early October.
to attend a meeting at Defiance County Department of Job and Family Services.
Meeting adjourned at
Approved for News Release: ______________________________
Otto L. Nicely, Commissioner