| DEFIANCE COUNTY ENGINEER | |||||||||||||||||||||||
| Canal Road Reconstruction | |||||||||||||||||||||||
| Bid Date: | Monday, July 11, 2011 | ||||||||||||||||||||||
| Engineer's Estimate: | $646,924.20 | ||||||||||||||||||||||
| Gerken Paving, Inc | Heer Excavating, Inc | Vernon Nagel, Inc | Miller Construction Group | Tenmile Creek Excavating | Klink Group | Crestline Paving | |||||||||||||||||
| Napoleon, OH | Archbold, OH | Napoleon, OH | Archbold, OH | Detroit, MI | Ashley, IN | Toledo, OH | |||||||||||||||||
| UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | ||||||||||
| ITEM | DESCRIPTION | QTY. | COST | COST | COST | COST | COST | COST | COST | COST | COST | COST | COST | COST | COST | COST | |||||||
| ROADWAY | |||||||||||||||||||||||
| Item | Description | Quantity | Units | Unit | Amount | Unit | Amount | Unit | Amount | Unit | Amount | Unit | Amount | Unit | Amount | Unit | Amount | ||||||
| Roadway | |||||||||||||||||||||||
| 204 | Clearing and Grubbing | 1 | Lump | $1,000.00 | $1,000.00 | $6,800.00 | $6,800.00 | $3,000.00 | $3,000.00 | ||||||||||||||
| 202 | Wearing Course Removed | 381 | Sq. Yd. | $5.00 | $1,905.00 | $15.00 | $5,715.00 | $9.00 | $3,429.00 | ||||||||||||||
| 202 | Pavement Removed for Stockpiling, As Per Plan | 18,266 | Sq. Yd. | $5.00 | $91,330.00 | $3.50 | $63,931.00 | $3.60 | $65,757.60 | ||||||||||||||
| 203 | Excavation, As Per Plan | 8611 | Cu. Yd. | $7.40 | $63,721.40 | $3.00 | $25,833.00 | $8.00 | $68,888.00 | ||||||||||||||
| 203 | Embankment | 6072 | Cu. Yd. | $7.40 | $44,932.80 | $3.80 | $23,073.60 | $9.50 | $57,684.00 | ||||||||||||||
| Special | Mailbox Support System, Single | 2 | Each | $150.00 | $300.00 | $150.00 | $300.00 | $90.00 | $180.00 | ||||||||||||||
| Erosion Control | |||||||||||||||||||||||
| 659 | Seeding and Mulching | 28,607 | Sq. Yd. | $0.40 | $11,442.80 | $0.40 | $11,442.80 | $0.40 | $11,442.80 | ||||||||||||||
| 659 | Comercial Fertilizer | 2.6 | Ton | $390.00 | $1,014.00 | $390.00 | $1,014.00 | $390.00 | $1,014.00 | ||||||||||||||
| 659 | Water | 62 | M Gal | $0.01 | $0.62 | $5.00 | $310.00 | $0.10 | $6.20 | ||||||||||||||
| Pavement | |||||||||||||||||||||||
| 206 | 16" Lime Stabilized Subgrade | 23,312 | Sq. Yd. | $4.18 | $97,444.16 | $3.70 | $86,254.40 | $4.55 | $106,069.60 | ||||||||||||||
| 206 | Lime | 988 | Tons | $80.00 | $79,040.00 | $130.00 | $128,440.00 | $110.00 | $108,680.00 | ||||||||||||||
| 411 | 6" Stabilized Crushed Aggregate | 1062 | Tons | $15.00 | $15,930.00 | $20.00 | $21,240.00 | $22.00 | $23,364.00 | ||||||||||||||
| 408 | Prime Coat (0.35 Gal/Sq. Yd.) | 4610 | Gal | $2.85 | $13,138.50 | $1.50 | $6,915.00 | $1.00 | $4,610.00 | ||||||||||||||
| 605 | Aggregate Drains | 2803 | Foot | $5.00 | $14,015.00 | $3.00 | $8,409.00 | $7.00 | $19,621.00 | ||||||||||||||
| 605 | 6" Shallow Pipe Underdrain | 1191 | Foot | $6.50 | $7,741.50 | $8.00 | $9,528.00 | $9.00 | $10,719.00 | ||||||||||||||
| 609 | Combination Curb & Gutter, Type 2 | 1191 | Foot | $11.00 | $13,101.00 | $13.00 | $15,483.00 | $14.00 | $16,674.00 | ||||||||||||||
| Pavement Recycling (FDR) | |||||||||||||||||||||||
| Special | Recycling Pavement per FDR specs | 22,356 | Sq. Yd. | $4.70 | $ 105,073.20 | $4.00 | $ 89,424.00 | $4.78 | $ 106,861.68 | ||||||||||||||
| FDR 2.1.4 | Portland Cement | 219 | Tons | $98.00 | $ 21,462.00 | $98.00 | $ 21,462.00 | $98.00 | $ 21,462.00 | ||||||||||||||
| FDR2.1.1 | Emulsion | 23,532 | Gal | $2.12 | $ 49,887.84 | $2.10 | $ 49,417.20 | $2.12 | $ 49,887.84 | ||||||||||||||
| Traffic Control | |||||||||||||||||||||||
| 614 | Maintaining Traffic, As Per Plan | 1 | Lump | $5,500.00 | $5,500.00 | $2,000.00 | $2,000.00 | $6,000.00 | $6,000.00 | ||||||||||||||
| 623 | Construction Layout Stakes | 1 | Lump | $10,500.00 | $10,500.00 | $8,000.00 | $8,000.00 | $5,900.00 | $5,900.00 | ||||||||||||||
| 624 | Mobilization | 1 | Lump | $20,000.00 | $20,000.00 | $6,000.00 | $6,000.00 | $7,000.00 | $7,000.00 | ||||||||||||||
| Miscellaneous | |||||||||||||||||||||||
| 604 | Monument Assemblies | 1 | Each | $700.00 | $700.00 | $1,000.00 | $1,000.00 | $683.06 | $683.06 | ||||||||||||||
| TOTAL | NO BID | NO BID | NO BID | $669,179.82 | $591,992.00 | NO BID | $698,933.78 | ||||||||||||||||
| Defiance County Engineer's Office | |||||||||||||||||||||||
| 2011 Young Rd Cement Stabilization/Estimate $23,381.00 | |||||||||||||||||||||||
| BIDS OPEN: | Monday, July 11, 2011 | ||||||||||||||||||||||
| 10:00 AM | |||||||||||||||||||||||
| Gerken Paving, Inc | Heer Excavating | Vernon Nagel, Inc | Miller Construction Group | Tenmile Creek Excavating | Klink Group | Crestline Paving | |||||||||||||||||
| Napoleon, OH | Archbold, OH | Napoleon, OH | Archbold, OH | Detroit, MI | Ashley, IN | Toledo, OH | |||||||||||||||||
| Item | Description | Quantity | Units | ||||||||||||||||||||
| Special | Full Depth, Chemical Stabilized Base Course (12",12") | 2867 | SY | $2.76 | $7,912.92 | $3.70 | $10,607.90 | $3.17 | $9,088.39 | ||||||||||||||
| Young Road 12" Pass 1,12" Pass 2, 16' wide | |||||||||||||||||||||||
| Special | Portland Cement | 81 | Tons | $98.00 | $7,938.00 | $98.00 | $7,938.00 | $100.00 | $8,100.00 | ||||||||||||||
| Special | Water | 25 | M Gal | $10.00 | $250.00 | $15.00 | $375.00 | $10.00 | $250.00 | ||||||||||||||
| 624 | Mobilization | 1 | Each | $2,500.00 | $2,500.00 | $500.00 | $500.00 | $3,000.00 | $3,000.00 | ||||||||||||||
| 614 | Traffic Control | 1 | Each | $200.00 | $200.00 | $500.00 | $500.00 | $900.00 | $900.00 | ||||||||||||||
| NO BID | NO BID | NO BID | $18,800.92 | $19,920.90 | NO BID | $21,338.39 | |||||||||||||||||