Defiance County Engineer's Office
DEF-TR 106-2.80 Casebeer-Miller Road Bridge Re-Bid
BID DATE:   Monday, March 26, 2007 
Engineer's Estimate: $212,923.00
R.G. Zachrich Construction
Defiance, OH
ESTIMATED UNIT TOTAL
ITEM DESCRIPTION QTY. PRICE PRICE
   
ROADWAY    
201 1 Lump Clearing and Grubbing    $  2,000.00  $         2,000.00  
202 56 Foot Guardrail removed    $        2.00  $            112.00  
202 51 Foot Pipe removed    $        7.00  $            357.00  
203 166 CY Excavation    $        8.75  $         1,452.50  
203 70 CY Embankment    $      23.00  $         1,610.00  
204 304 SY Subgrade Compaction    $        0.80  $            243.20  
606 100 Foot Guardrail, Type 5, As per plan    $      19.35  $         1,935.00  
606 4 Each Bridge Terminal Assembly, Type 4    $     640.00  $         2,560.00  
606 4 Each Type A Anchor Assembly    $     980.00  $         3,920.00  
   
EROSION CONTROL    
601 29 CY Rock Channel Protection, Type B with filter    $      67.00  $         1,943.00  
832 1 Lump Erosion Control    $  3,000.00  $         3,000.00  
659 468 SY Seeding and Mulching    $        4.20  $         1,965.60  
659 0.04 Ton Commercial Fertilizer    $     472.50  $              18.90  
659 1 M Gallon Water    $        1.00  $                1.00  
   
DRAINAGE    
603 50 Foot 6" Conduit, Type F    $        4.00  $            200.00  
603 50 Foot 8" Conduit, Type F    $        6.00  $            300.00  
603 50 Foot 10" Conduit, Type F    $        8.00  $            400.00  
603 60 Foot 12" Conduit, Type C    $      10.00  $            600.00  
603 50 Foot 12" Conduit, Type F    $      10.00  $            500.00  
   
PAVEMENT    
304 223 Tons Aggregate Base    $      23.00  $         5,129.00  
408 79 Gallon Prime Coat    $        2.00  $            158.00  
411 11 Tons Stabilized Crushed Aggregate    $      37.00  $            407.00  
448 16 Tons Asphalt Concrete Surface Course, Type 1, PG64-22    $     173.00  $         2,768.00  
448 22 Tons Asphalt Concrete Intermediate Course, Type 1, PG64-22    $     173.00  $         3,806.00  
   
STRUCTURE    
202 1 Lump Structure Removed    $  6,500.00  $         6,500.00  
503 1 Lump Unclassified Excavation    $  1,000.00  $         1,000.00  
Special 8 Each FRP Box Beam Bridge Member    $11,336.74  $        90,693.92  
Special 32 CY Lightweight Concrete    $     243.00  $         7,776.00  
Special 1 Lump FRP Rebar    $12,500.00  $        12,500.00  
704 1021 Each Splitface Concrete Masonry Block    $        4.55  $         4,645.55  
704 575 Each Solid Concrete Masonry Block    $        6.23  $         3,582.25  
Special 1688 SY High Strength Woven Polypropylene Fabric    $        3.50  $         5,908.00  
Special 222 SY Medium Strength Woven Polypropylene Fabric    $        6.19  $         1,374.18  
203 311 CY Granular Embankment #89 Stone    $      54.25  $        16,871.75  
203 25 CY Granular Embankment #304 Stone    $      54.25  $         1,356.25  
511 3.89 CY Class C Concrete, As Per Plan    $     400.00  $         1,556.00  
Special 1 Lump Beam Seat Construction    $     534.00  $            534.00  
517 50 Foot Railing (Deep Beam Rail with Steel Tubular Backup & Type 2 Steel Post and Anchor Bolt    $      52.75  $         2,637.50  
   
TRAFFIC CONTROL    
626 8 Each Barrier Reflector    $        7.85  $              62.80  
   
MAINTENANCE OF TRAFFIC    
614 1 Lump Maintaining Traffic    $  2,000.00  $         2,000.00  
623 1 Lump Construction Layout Stakes    $  1,600.00  $         1,600.00  
624 1 Lump Mobilization    $  4,500.00  $         4,500.00  
   
   
Total    $      200,484.40