| Harding Road (CR 195) Reconstruction | |||||||||||||||||
| Bid Date: April 23, 2007 10:00 am | |||||||||||||||||
| Engineer's Estimate: | $773,978.70 | ||||||||||||||||
| WARD | MILLER BROS | B HILL'Z | HEER | ZACHRICH | |||||||||||||
| CONSTRUCTION | CONSTRUCTION | EXCAVATING | EXCAVATING | LEASING | |||||||||||||
| Item | Description | Quantity | Units | Unit | Amount | Unit | Amount | Unit | Amount | Unit | Amount | Unit | Amount | ||||
| Price | Price | Price | Price | Price | |||||||||||||
| Roadway & Channel | |||||||||||||||||
| 201 | Clearing and Grubbing | 1 | Lump | $ 18,400.00 | $ 18,400.00 | $ 10,000.00 | $ 10,000.00 | $ 15,000.00 | $ 15,000.00 | $ 55,000.00 | $ 55,000.00 | $ 6,000.00 | $ 6,000.00 | ||||
| 202 | Pipe Removed 12" and under | 826 | Foot | $ 6.00 | $ 4,956.00 | $ 5.00 | $ 4,130.00 | $ 5.00 | $ 4,130.00 | $ 2.90 | $ 2,395.40 | $ 10.00 | $ 8,260.00 | ||||
| 202 | Pipe Removed 24" and under | 55 | Foot | $ 40.00 | $ 2,200.00 | $ 8.00 | $ 440.00 | $ 15.00 | $ 825.00 | $ 4.25 | $ 233.75 | $ 12.00 | $ 660.00 | ||||
| 202 | Guardrail Removal for Storage | 740 | Foot | $ 3.00 | $ 2,220.00 | $ 1.00 | $ 740.00 | $ 1.00 | $ 740.00 | $ 1.10 | $ 814.00 | $ 1.25 | $ 925.00 | ||||
| 202 | Wearing Course Removed | 2102 | Sq. Yd. | $ 2.00 | $ 4,204.00 | $ 1.85 | $ 3,888.70 | $ 2.00 | $ 4,204.00 | $ 2.00 | $ 4,204.00 | $ 2.10 | $ 4,414.20 | ||||
| 202 | Catch Basin Removed | 2 | Each | $ 200.00 | $ 400.00 | $ 150.00 | $ 300.00 | $ 100.00 | $ 200.00 | $ 125.00 | $ 250.00 | $ 250.00 | $ 500.00 | ||||
| 202 | Headwall Removed | 3 | Each | $ 300.00 | $ 900.00 | $ 150.00 | $ 450.00 | $ 50.00 | $ 150.00 | $ 125.00 | $ 375.00 | $ 500.00 | $ 1,500.00 | ||||
| 203 | Excavation, As Per Plan | 5418 | Cu. Yd. | $ 6.25 | $ 33,862.50 | $ 7.50 | $ 40,635.00 | $ 5.00 | $ 27,090.00 | $ 9.25 | $ 50,116.50 | $ 5.00 | $ 27,090.00 | ||||
| 203 | Embankment | 18684 | Cu. Yd. | $ 6.25 | $ 116,775.00 | $ 7.50 | $ 140,130.00 | $ 7.00 | $ 130,788.00 | $ 3.50 | $ 65,394.00 | $ 7.00 | $ 130,788.00 | ||||
| 204 | Subgrade Compaction | 15966 | Sq. Yd. | $ 0.50 | $ 7,983.00 | $ 0.50 | $ 7,983.00 | $ 1.00 | $ 15,966.00 | $ 0.45 | $ 7,184.70 | $ 0.80 | $ 12,772.80 | ||||
| Special | Mailbox Support System, Single | 9 | Each | $ 125.00 | $ 1,125.00 | $ 75.00 | $ 675.00 | $ 100.00 | $ 900.00 | $ 75.00 | $ 675.00 | $ 110.00 | $ 990.00 | ||||
| 606 | Guardrail Type 5 | 725 | Feet | $ 13.00 | $ 9,425.00 | $ 9.50 | $ 6,887.50 | $ 13.00 | $ 9,425.00 | $ 14.50 | $ 10,512.50 | $ 14.52 | $ 10,527.00 | ||||
| 606 | Bridge Terminal Assembly Type 4 | 2 | Each | $ 650.00 | $ 1,300.00 | $ 480.00 | $ 960.00 | $ 650.00 | $ 1,300.00 | $ 650.00 | $ 1,300.00 | $ 693.00 | $ 1,386.00 | ||||
| 606 | Type A Anchor Assembly | 2 | Each | $ 825.00 | $ 1,650.00 | $ 700.00 | $ 1,400.00 | $ 850.00 | $ 1,700.00 | $ 900.00 | $ 1,800.00 | $ 935.00 | $ 1,870.00 | ||||
| Erosion Control | |||||||||||||||||
| 601 | Rock Channel Protection, Type C w/ filter | 37 | Cu. Yd. | $ 25.00 | $ 925.00 | $ 30.00 | $ 1,110.00 | $ 40.00 | $ 1,480.00 | $ 55.00 | $ 2,035.00 | $ 60.00 | $ 2,220.00 | ||||
| SS 836 | Turf reinforcing mat - Type 1 | 300 | Sq. Yd. | $ 5.00 | $ 1,500.00 | $ 4.25 | $ 1,275.00 | $ 2.00 | $ 600.00 | $ 7.50 | $ 2,250.00 | $ 6.52 | $ 1,956.00 | ||||
| 660 | Sodding Staked | 100 | Sq. Yd. | $ 4.00 | $ 400.00 | $ 6.00 | $ 600.00 | $ 4.00 | $ 400.00 | $ 9.00 | $ 900.00 | $ 16.12 | $ 1,612.00 | ||||
| 659 | Seeding and Mulching | 31938 | Sq. Yd. | $ 0.30 | $ 9,581.40 | $ 0.28 | $ 8,942.64 | $ 0.40 | $ 12,775.20 | $ 0.35 | $ 11,178.30 | $ 0.65 | $ 20,759.70 | ||||
| 659 | Comercial Fertilizer | 2.87 | Ton | $ 400.00 | $ 1,148.00 | $ 395.00 | $ 1,133.65 | $ 400.00 | $ 1,148.00 | $ 500.00 | $ 1,435.00 | $ 400.00 | $ 1,148.00 | ||||
| 659 | Water | 85 | M Gal | $ 1.00 | $ 85.00 | $ 10.00 | $ 850.00 | $ 1.00 | $ 85.00 | $ 6.00 | $ 510.00 | $ 2.75 | $ 233.75 | ||||
| 832 | Erosion Control | 1 | Lump | $ 10,000.00 | $ 10,000.00 | $ 10,000.00 | $ 10,000.00 | $ 10,000.00 | $ 10,000.00 | $ 10,000.00 | $ 10,000.00 | $ 10,000.00 | $ 10,000.00 | ||||
| 832 | Storm Water Pollution Prevention Plan | 1 | Each | $ 1,500.00 | $ 1,500.00 | $ 1,500.00 | $ 1,500.00 | $ 1,500.00 | $ 1,500.00 | $ 3,000.00 | $ 3,000.00 | $ 3,500.00 | $ 3,500.00 | ||||
| Drainage | |||||||||||||||||
| 602 | Concrete Masonary | 2.14 | Cu. Yd. | $ 850.00 | $ 1,819.00 | $ 800.00 | $ 1,712.00 | $ 100.00 | $ 214.00 | $ 650.00 | $ 1,391.00 | $ 1,500.00 | $ 3,210.00 | ||||
| 603 | 4" Conduit, Type E | 100 | Foot | $ 2.00 | $ 200.00 | $ 1.00 | $ 100.00 | $ 3.00 | $ 300.00 | $ 7.50 | $ 750.00 | $ 5.00 | $ 500.00 | ||||
| 603 | 4" Conduit, Type F | 100 | Foot | $ 2.50 | $ 250.00 | $ 1.00 | $ 100.00 | $ 3.00 | $ 300.00 | $ 7.50 | $ 750.00 | $ 9.00 | $ 900.00 | ||||
| 603 | 6" Conduit, Type E | 100 | Foot | $ 3.00 | $ 300.00 | $ 1.50 | $ 150.00 | $ 4.00 | $ 400.00 | $ 8.50 | $ 850.00 | $ 8.25 | $ 825.00 | ||||
| 603 | 6" Conduit, Type F | 100 | Foot | $ 3.50 | $ 350.00 | $ 1.50 | $ 150.00 | $ 4.00 | $ 400.00 | $ 8.50 | $ 850.00 | $ 14.00 | $ 1,400.00 | ||||
| 603 | 8" Conduit, Type E | 100 | Foot | $ 3.50 | $ 350.00 | $ 2.00 | $ 200.00 | $ 5.00 | $ 500.00 | $ 10.50 | $ 1,050.00 | $ 10.00 | $ 1,000.00 | ||||
| 603 | 8" Conduit, Type F | 100 | Foot | $ 4.00 | $ 400.00 | $ 2.00 | $ 200.00 | $ 5.00 | $ 500.00 | $ 10.50 | $ 1,050.00 | $ 15.00 | $ 1,500.00 | ||||
| 603 | 10" Conduit, Type E | 60 | Foot | $ 4.00 | $ 240.00 | $ 3.00 | $ 180.00 | $ 32.00 | $ 1,920.00 | $ 12.00 | $ 720.00 | $ 11.00 | $ 660.00 | ||||
| 603 | 10" Conduit, Type F | 50 | Foot | $ 5.00 | $ 250.00 | $ 3.00 | $ 150.00 | $ 7.00 | $ 350.00 | $ 11.00 | $ 550.00 | $ 18.00 | $ 900.00 | ||||
| 603 | 12" Conduit, Type B | 50 | Foot | $ 10.00 | $ 500.00 | $ 4.00 | $ 200.00 | $ 8.00 | $ 400.00 | $ 30.75 | $ 1,537.50 | $ 44.00 | $ 2,200.00 | ||||
| 603 | 12" Conduit, Type C As Per Plan* | 500 | Foot | $ 15.00 | $ 7,500.00 | $ 22.00 | $ 11,000.00 | $ 23.00 | $ 11,500.00 | $ 15.00 | $ 7,500.00 | $ 43.00 | $ 21,500.00 | ||||
| 603 | 12" Conduit, Type D | 112 | Foot | $ 15.50 | $ 1,736.00 | $ 12.00 | $ 1,344.00 | $ 25.00 | $ 2,800.00 | $ 11.00 | $ 1,232.00 | $ 31.00 | $ 3,472.00 | ||||
| 603 | 12" Conduit, Type E | 100 | Foot | $ 4.00 | $ 400.00 | $ 4.00 | $ 400.00 | $ 8.00 | $ 800.00 | $ 9.75 | $ 975.00 | $ 15.00 | $ 1,500.00 | ||||
| 603 | 12" Conduit, Type F | 100 | Foot | $ 4.00 | $ 400.00 | $ 4.00 | $ 400.00 | $ 8.00 | $ 800.00 | $ 9.75 | $ 975.00 | $ 43.00 | $ 4,300.00 | ||||
| 603 | 18" Conduit Type C 706.02 | 18 | Foot | $ 31.00 | $ 558.00 | $ 75.00 | $ 1,350.00 | $ 48.00 | $ 864.00 | $ 100.00 | $ 1,800.00 | $ 52.00 | $ 936.00 | ||||
| 603 | 21" Conduit, Type C As Per Plan* | 416 | Foot | $ 30.00 | $ 12,480.00 | $ 32.00 | $ 13,312.00 | $ 33.00 | $ 13,728.00 | $ 27.00 | $ 11,232.00 | $ 37.80 | $ 15,724.80 | ||||
| 603 | 24" Conduit, Type C As Per Plan* | 532 | Foot | $ 30.00 | $ 15,960.00 | $ 32.00 | $ 17,024.00 | $ 33.00 | $ 17,556.00 | $ 30.00 | $ 15,960.00 | $ 37.80 | $ 20,109.60 | ||||
| 603 | 30" Conduit, Type B 706.02 | 74 | Foot | $ 85.00 | $ 6,290.00 | $ 130.00 | $ 9,620.00 | $ 68.00 | $ 5,032.00 | $ 62.00 | $ 4,588.00 | $ 84.00 | $ 6,216.00 | ||||
| 603 | 30" Conduit, Type C As Per Plan* | 250 | Foot | $ 37.00 | $ 9,250.00 | $ 43.00 | $ 10,750.00 | $ 43.00 | |||||||||