DEFIANCE COUNTY ENGINEER
 
2008 PAVEMENT MARKING
Bid Date:   3/10/2008
Engineer's Estimate: $167,026.25
AERO-MARK, Inc. Ogelsby Construction, Inc.
Streetsboro, OH Norwalk, OH
        UNIT TOTAL UNIT TOTAL
ITEM DESCRIPTION QTY.   COST COST COST COST
643 Stop Line 81 Ea.  $  75.00  $         6,075.00  $  73.00  $             5,913.00
               
643 RR Symbol Mkg. 6 Ea.  $360.00  $         2,160.00  $390.00  $             2,340.00
               
643 Word on Pavement "SCHOOL"  5 Ea.  $390.00  $         1,950.00  $420.00  $             2,100.00
               
643 Center Line 126.75 Mile  $111.00  $       14,069.25  $117.00  $          14,829.75
               
643 White Edge Line 224.06 Mile  $101.00  $       22,630.06  $106.97  $          23,967.70
               
643 Polyester Material  5,247 Gal.  $  21.64  $    113,545.08  $  22.10  $        115,958.70
               
643 Spotting Centerline 36.61 Mile  $     7.00  $            256.27  $     7.00  $                256.27
               
643 Miles of No Passing Zone Survey (Special) 5 Mile  $248.00  $         1,240.00  $150.00  $                750.00
               
643 Miles of Index Marking (Special) 5 Mile  $     7.00  $              35.00  $  10.00  $                  50.00
               
624 Mobilization 2 Ea.  $500.00  $         1,000.00  $400.00  $                800.00
           $ 162,960.66    $    166,965.42