DEFIANCE COUNTY ENGINEER
   
SR 2/W. High St. Turn Lane
Bid Date: Monday, September 10, 2012
Engineer's Estimate: $305,000.00
Crestline Paving & Excavating Gerken Paving, Inc Ward Construction Vernon Nagel, Inc
Toledo, OH  Napoleon, OH  Leipsic, OH  Napoleon, OH 
                   
        UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
ITEM DESCRIPTION QTY.   COST COST COST COST COST COST COST COST
ROADWAY
Item Description Quantity Units  Unit   Amount    Unit   Amount    Unit   Amount    Unit   Amount
                             
  Roadway                          
201 Clearing and Grubbing 1 Lump  $          1,000.00 $1,000.00   $4,000.00 $4,000.00     $0.00   $10,000.00 $10,000.00
202 Pipe Removed 183 Foot  $               11.00 $2,013.00   $8.00 $1,464.00     $0.00   $20.00 $3,660.00
203 Excavation, As Per Plan 567 Cu. Yd.  $               38.00 $21,546.00   $22.00 $12,474.00     $0.00   $24.00 $13,608.00
203 Embankment 756 Cu. Yd.  $               18.00 $13,608.00   $22.00 $16,632.00     $0.00   $24.00 $18,144.00
204 Subgrade Compaction 2049 Sq. Yd.  $                  1.00 $2,049.00   $1.00 $2,049.00     $0.00   $1.00 $2,049.00
Special Mailbox 3 Each  $             120.00 $360.00   $125.00 $375.00         $100.00 $300.00
  Erosion Control                          
659 Seeding and Mulching 3755 Sq. Yd.  $                  1.10 $4,130.50   $1.10 $4,130.50     $0.00   $1.10 $4,130.50
659 Commercial Fertilizer 0.4 Ton  $             500.00 $200.00   $500.00 $200.00     $0.00   $500.00 $200.00
659 Water 8 M Gal  $                  1.00 $8.00   $1.00 $8.00     $0.00   $1.00 $8.00
832 Erosion Control ($3000 carried to the Bid proposal) 1 Each  $          3,000.00 $3,000.00   $3,000.00 $3,000.00     $0.00   $3,500.00 $3,500.00
832 Storm Water Pollution Prevention Plan 1 Lump  $          1,500.00 $1,500.00   $1,500.00 $1,500.00     $0.00   $3,500.00 $3,500.00
  Drainage                          
603 12" Conduit, Type C, As Per Plan 435 Foot  $               40.00 $17,400.00   $25.00 $10,875.00     $0.00   $45.00 $19,575.00
604 Manhole Adjusted to Grade 1 Each  $             888.00 $888.00   $550.00 $550.00     $0.00   $500.00 $500.00
604 Catch Basin, No. 5 without Apron, As Per Plan 5 Each  $          1,630.00 $8,150.00   $1,750.00 $8,750.00     $0.00   $2,000.00 $10,000.00
638 Valve Box adjusted to Grade 1 Each  $             300.00 $300.00   $250.00 $250.00     $0.00   $250.00 $250.00
  Pavement                           
301 Asphalt Concrete Base 376 Tons  $               80.00 $30,080.00   $75.00 $28,200.00     $0.00   $75.00 $28,200.00
304 Aggregate Base 647 Gal  $               31.00 $20,057.00   $30.00 $19,410.00     $0.00   $35.00 $22,645.00
407 Tack Coat (0.10 Gal/Sq. Yd.) 397 Gal  $                  2.85 $1,131.45   $2.00 $794.00     $0.00   $2.00 $794.00
411 Stabilized Crushed Aggregate 297 Tons  $               30.00 $8,910.00   $31.50 $9,355.50     $0.00   $40.00 $11,880.00
448 Asphalt Concrete Intermediate Course Type 2 PG 64-22, As Per Plan 241 Tons  $               99.00 $23,859.00   $88.50 $21,328.50     $0.00   $88.50 $21,328.50
448 Asphalt Concrete Surface Course Type 1 PG 64-22, As Per Plan 412 Tons  $             100.00 $41,200.00   $90.00 $37,080.00     $0.00   $90.00 $37,080.00
  Traffic Control                          
644 Edge Line 0.38 Mile  $          4,000.00  $        1,520.00   $4,000.00 $1,520.00     $0.00   $4,000.00 $1,520.00
644 Center Line 0.33 Mile  $          8,000.00 $2,640.00   $8,000.00 $2,640.00     $0.00   $8,000.00 $2,640.00
644 Lane Line 0.06 Mile  $          4,000.00 $240.00   $4,000.00 $240.00     $0.00   $4,000.00 $240.00
644 Channelizing Line 909 Foot  $                  1.50 $1,363.50   $1.50 $1,363.50     $0.00   $1.50 $1,363.50
644 Lane Arrow 2 Each  $             100.00 $200.00   $100.00 $200.00     $0.00   $100.00 $200.00
  Miscellaneous                          
614 Maintaining Traffic 1 Lump  $          2,000.00 $2,000.00   $17,000.00 $17,000.00     $0.00   $15,000.00 $15,000.00
623 Construction Layout Stakes 1 Lump  $          1,510.00 $1,510.00   $3,500.00 $3,500.00     $0.00   $4,500.00 $4,500.00
624 Mobilization 1 Lump  $        11,146.00 $11,146.00   $5,000.00 $5,000.00     $0.00   $10,000.00 $10,000.00
                             
                     
TOTAL   $222,009.45     $213,889.00     NO BID     $246,815.50