DEFIANCE COUNTY ENGINEER
CR 424 Shoulder Widening
Bid Date: Monday, July 23, 2018
Engineer's Estimate: $1,432,193.00
RG Zachrich Construction Gerken Paving, Inc Geddis Paving & Excavating Helms & Sons Excavating
Defiance, OH  Napoleon, OH  Toledo, OH Findlay, OH 
                 
        UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
ITEM DESCRIPTION QTY.   COST COST COST COST COST COST COST COST
ROADWAY
Item Description Quantity Units  Unit   Amount    Unit   Amount    Unit   Amount Unit  Amount
                           
  Roadway                        
202 Curb and Gutter Removal 2717 Feet $3.00 $8,151.00   $8.00 $21,736.00     $0.00   $0.00
202 Sidewalk Removal 205 Feet $3.00 $615.00   $9.50 $1,947.50     $0.00   $0.00
202 Guardrail Removal 10,763 Feet $1.50 $16,144.50   $1.50 $16,144.50     $0.00   $0.00
203 Excavation (curb) As per plan 2,717 Feet $7.00 $19,019.00   $6.00 $16,302.00     $0.00   $0.00
203 Excavation (Filter trench) As per plan 2300 Feet $10.00 $23,000.00   $5.00 $11,500.00     $0.00   $0.00
203 Excavation (widening) As per plan 44010 Feet $2.00 $88,020.00   $2.40 $105,624.00     $0.00   $0.00
203 Embankment, As per plan 2717 Feet $5.00 $13,585.00   $4.70 $12,769.90     $0.00   $0.00
204 Subgrade Compaction 15740 SY $1.50 $23,610.00   $0.35 $5,509.00     $0.00   $0.00
407 Tack Coat 5868 Gal $2.25 $13,203.00   $2.25 $13,203.00     $0.00   $0.00
411 Stabilized Crushed Aggregate, As Per plan 680 Tons $30.50 $20,740.00   $31.50 $21,420.00     $0.00   $0.00
441 Asphalt Concrete Surface Course, Type 1 (448) PG64-22, As per plan 5436 Tons $84.00 $456,624.00   $84.00 $456,624.00     $0.00   $0.00
452 7" Non Reinforced concrete Pavement, As per plan 3056 CY $102.00 $311,712.00   $100.00 $305,600.00     $0.00   $0.00
605 4" Base Pipe Underdrain 2668 Feet $5.00 $13,340.00   $6.00 $16,008.00     $0.00   $0.00
606 Guardrail, Type MGS with long posts 10273  Feet $23.50 $241,415.50   $23.50 $241,415.50     $0.00   $0.00
606 Type A Anchor Assembly, Type MGS 26 Each $965.00 $25,090.00   $965.00 $25,090.00     $0.00   $0.00
609 Curb, Type 7 2717 Feet $13.00 $35,321.00   $12.50 $33,962.50     $0.00   $0.00
611 Catch Basin Adjusted to Grade, As per plan 7 Each $728.00 $5,096.00   $750.00 $5,250.00     $0.00   $0.00
611 Manhole Adjusted to Grade 17 Each $535.00 $9,095.00   $900.00 $15,300.00     $0.00   $0.00
643 Edge Line 8.34 Mile $1,260.00 $10,508.40   $1,260.00 $10,508.40     $0.00   $0.00
643 Center Line 4.17 Mile $1,910.00 $7,964.70   $1,910.00 $7,964.70     $0.00   $0.00
703 #57 Stone 444 Tons $45.00 $19,980.00   $42.00 $18,648.00     $0.00   $0.00
703 Filter Sand,703.20 341 Tons $40.00 $13,640.00   $34.00 $11,594.00     $0.00   $0.00
712 Geotextile Fabric, Type A 1656 SY $3.00 $4,968.00   $1.10 $1,821.60     $0.00   $0.00
Special Formed Construction Joint 10 Each $500.00 $5,000.00   $850.00 $8,500.00     $0.00   $0.00
832 Erosion Control 1 Each $1,000.00 $1,000.00   $1,000.00 $1,000.00   $1,000.00 $1,000.00 $1,000.00 $1,000.00
832 Stormwater Pollution Prevention Plan 1 Lump $8,516.00 $8,516.00   $2,275.00 $2,275.00     $0.00   $0.00
614 Maintaining Traffic 1 Lump $48,000.00 $48,000.00   $30,000.00 $30,000.00     $0.00   $0.00
624 Mobilization 1 Lump $52,000.00 $52,000.00   $15,000.00 $15,000.00     $0.00   $0.00
                           
                   
TOTAL   $1,495,358.10     $1,432,717.60     NO BID   NO BID