DEFIANCE COUNTY ENGINEER
 
2018 PAVEMENT MARKING
Bid Date:   4/2/2018
AERO-MARK, Inc. Ogelsby Construction, Inc.
Streetsboro, OH Norwalk, OH
        UNIT TOTAL UNIT TOTAL
ITEM DESCRIPTION QTY.   COST COST COST COST
643 Stop Line 57 Ea.  $   109.00  $         6,213.00  $120.00  $             6,840.00
               
643 RR Symbol Mkg. 4 Ea.  $   575.00  $         2,300.00  $550.00  $             2,200.00
               
643 Word on Pavement "SCHOOL"  3 Ea.  $   575.00  $         1,725.00  $550.00  $             1,650.00
               
643 Center Line 46.41 Mile  $   212.00  $         9,838.92  $202.00  $             9,374.82
               
643 Center Line (<500') 3.79 Mile  $   515.00  $         1,951.85  $500.00  $             1,895.00
               
643 White Edge Line 85.51 Mile  $   178.00  $       15,220.78  $185.00  $          15,819.35
               
643 White Edge Line (<500') 3 Mile  $   515.00  $         1,545.00  $500.00  $             1,500.00
               
643 Polyester Material (Mainline) 2,110 Gal.  $      26.07  $       55,007.70  $  27.65  $          58,341.50
643 Polyester Material (Patching) 104 Gal.  $      26.07  $         2,711.28  $  27.65  $             2,875.60
643 Spotting Centerline 50.2 Mile  $      20.00  $         1,004.00  $  25.00  $             1,255.00
624 Mobilization 2 Ea.  $   500.00  $         1,000.00 1092.00  $             2,184.00
       
643 No Passing Zone Study 1 Mile  $   247.90  $            247.90 600.00  $                600.00
   $   98,765.43    $    104,535.27