| DEFIANCE COUNTY ENGINEER | |||||||||||
| Banner School Rd Connection | |||||||||||
| Bid Date: | 3/14/2024 | ||||||||||
| Engineer's Estimate: | $420,000.00 | ||||||||||
| RG Zachrich Constr. | Gerken Paving, Inc | Vernon Nagel | Ward Construction | ||||||||
| Defiance OH | Napoleon, OH | Napoleon, OH | Leipsic, OH | ||||||||
| UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | ||||
| Item | Description | Quantity | Units | PRICE | COST | PRICE | COST | PRICE | COST | PRICE | COST | 
| 202 | Pavement Removed, As Per Plan | 3474 | SY | $ 6.00 | $ 20,844.00 | $ - | $ 10.10 | $ 35,087.40 | $ 5.50 | $ 19,107.00 | |
| 203 | Excavation | 902 | CY | $ 15.00 | $ 13,530.00 | $ - | $ 30.50 | $ 27,511.00 | $ 23.00 | $ 20,746.00 | |
| 203 | Embankment | 3497 | CY | $ 24.50 | $ 85,676.50 | $ - | $ 22.00 | $ 76,934.00 | $ 12.00 | $ 41,964.00 | |
| Special | Spreading Recycled Materials | 6044 | SY | $ 3.00 | $ 18,132.00 | $ - | $ 4.50 | $ 27,198.00 | $ 4.00 | $ 24,176.00 | |
| 206 | Cement Stabilized Subgrade, 16" Deep | 6044 | SY | $ 6.00 | $ 36,264.00 | $ - | $ 5.00 | $ 30,220.00 | $ 4.95 | $ 29,917.80 | |
| 206 | Cement | 213 | Tons | $ 268.00 | $ 57,084.00 | $ - | $ 224.00 | $ 47,712.00 | $ 200.00 | $ 42,600.00 | |
| 407 | Tack Coat | 693 | Gal | $ 2.75 | $ 1,905.75 | $ - | $ 2.75 | $ 1,905.75 | $ 3.00 | $ 2,079.00 | |
| 411 | 3" Stabilized Crushed Aggregate | 407 | Tons | $ 43.00 | $ 17,501.00 | $ - | $ 43.00 | $ 17,501.00 | $ 34.00 | $ 13,838.00 | |
| 304 | 12" Aggregate Base (Drives) | 170 | SY | $ 35.00 | $ 5,950.00 | $ - | $ 83.50 | $ 14,195.00 | $ 36.00 | $ 6,120.00 | |
| 452 | 7" Non Reinforced Concrete Pavement, As per plan | 396 | CY | $ 148.00 | $ 58,608.00 | $ - | $ 199.50 | $ 79,002.00 | $ 182.00 | $ 72,072.00 | |
| 823 | 1.5" Asphalt Concrete Surface Course Type 1 (448) PG64-22, As Per Plan | 1061 | Ton | $ 92.50 | $ 98,142.50 | $ - | $ 92.50 | $ 98,142.50 | $ 112.00 | $ 118,832.00 | |
| 832 | Erosion Control | 1 | Each | $ 3,000.00 | $ 3,000.00 | $ - | $ 3,000.00 | $ 3,000.00 | $ 3,000.00 | $ 3,000.00 | |
| 832 | Storm Water Pollution Prevention Plan | 1 | Lump | $ 2,000.00 | $ 2,000.00 | $ - | $ 1,585.00 | $ 1,585.00 | $ 1,600.00 | $ 1,600.00 | |
| 832 | Storm Water Pollution Prevention Inspections | 1 | Lump | $ 1,800.00 | $ 1,800.00 | $ - | $ 3,520.00 | $ 3,520.00 | $ 4,000.00 | $ 4,000.00 | |
| 832 | Storm Water Pollution Prevention Inspection Software | 1 | Lump | $ 2,800.00 | $ 2,800.00 | $ - | $ 2,540.00 | $ 2,540.00 | $ 3,000.00 | $ 3,000.00 | |
| 614 | Maintaining Traffic | 1 | Lump | $ 6,000.00 | $ 6,000.00 | $ - | $ 11,316.35 | $ 11,316.35 | $ 17,000.00 | $ 17,000.00 | |
| 624 | Mobilization | 1 | Lump | $ 30,000.00 | $ 30,000.00 | $ - | $ 10,000.00 | $ 10,000.00 | $ 11,000.00 | $ 11,000.00 | |
| Total | $ 459,237.75 | Total | NO BID | Total | $ 487,370.00 | Total | $ 431,051.80 | ||||